How the project is progressing

Phase 2

Start of Project: September 2010Arnhem Wharf School

Week 1 – Site compound is established and contractor’s welfare facilities are installed on site.

Week 2 – Site clearance has commenced as shown in the photograph.

 

 

 

October 2010: Arnhem Wharf School

Week 3-4 – Hoardings are erected within the school to separate the children and staff from the site areas occupied by the contractor. Paving and planting are all stripped out and removed from site in the area of the new extension building.

Weeks 5-6 – The site has been cleared and excavations have commenced as shown in the photograph.

 

 

November 2010: Arnhem Wharf School

Week 7 – The site for the new extension has been excavated, down to new foundation level, including the remains of a building basement that had occupied the site in the past.